Wednesday, 30 April 2014

Modular Kitchens at 99000



Complete woodwork for your kitchen at just Rs 99,000/-


We use 100% waterproof plywood to manufacture modular kitchens with maximum life. Along with this all hardware fitted with our kitchens are quality products that comes with lifelong warranty of 15yrs.

Specifications:

a. Modular finish
b. Complete wood work
c. Quality German hinghes
d. Stainless steel baskets (6 number)
e. Bottle rack, MTU (@ extra cost) for your extra storage

Note: This doesnot include granite top / gas stove / electrical chimney. Above offer is valid for kitchen of 8 x 6 ft. dimension

We also undertake

• Wardrobes
• Dining table
• Sofa
• Study table

For further details contact us at www.aakar-interiors.com/offer  or following numbers
9886019616 / 8861985156




Tuesday, 11 October 2011

Understanding Fixed Unit, Fixed Work and Fixed Duration tasks

Before going through let us understand what is Unit, Duration and work in MS Project and how they are related.
Unit :  Refers to “Resource”.  Measured as “% Allocation”
Work:    Refers to amount of “Work” to be completed.  Measured as “Hrs”
Duration: Refers to time required to complete work.  Measured as “Days” (Man days etc)
All above are related to each other with formula:
                Duration x Units = Work
Any task created in MS Project defaults to “Fixed Units”.  MS Project supports following types of tasks creation:
Fixed Unit:  A task in which the assigned units [or resources] is a fixed value and any changes to the amount of work or the task’s duration do not affect the task’s units.  Impact of change in Work, Duration or unit of work in a Fixed Unit task can be illustrated as follow:
Fixed units tasks behavior in MS Project
Fixed Unit

Fixed Duration:  A task in which the duration is a fixed value and any changes to the work or the assigned units [that is, resources] don’t affect the task’s duration.  Impact of change in Work, Duration or unit of work in a Fixed Duration task can be illustrated as follow:
Fixed Duration behavior
Fixed Duration

Fixed Work:  A task in which the amount of work is a fixed value and any changes to the task’s duration or the number of assigned units [or resources] do not affect the task’s work.  Impact of change in Work, Duration or unit of work in a Fixed Work  task can be illustrated as follow:
Fixed Work Task
Fixed Work
Thus using this simple calculation and understanding impact of changes in different types of tasks, one can easily predict changes MS Project is going to make on given tasks.
That’s all